Tunnel Jumeirah Palm Island, United Arab Emirates

Project data

Location: Dubai, United Arab Emirates

  • length of tunnel: 996 m
  • total length: 1.4 km
  • width/ height of cross-section: 38 m / 9.16 m
  • structure: tunnel in open-type construction with separate casting method, three-cell rectangular cross-section

Requirements

  • 25 m long concreting sections
  • fabrication of bottom plate, two shear walls and slab after each other

Customer

Al Naboodah Engineering Services L.L.C., Dubai

Benefit to customer

  • fast cycle sequences
  • easy handling
  • versatile utilisation
  • application of 200,000 m³ of concrete in a construction time of only 11 months
Tunnel Jumeirah Palm Island Statement: Walter Freitag, Construction Manager
Walter Freitag
Construction Manager

We were able to achieve a fast cycle sequence with the PERI systems. They are easy to handle and offer many different uses. On top of this, PERI offered us the required technical support at the jobsite.

PERI solution

  • tunnel formwork solution from system components